Case Study

Rolla National Airport Runway Rehabilitation

  • asphalt
  • Service Page Icon

This project consisted of reconstruction Runway 4/22 at the the Rolla National Airport in Vichy, Missouri. Construction began with pulverization of the existing asphalt and subgrade. The subgrade was then cut to final elevation followed by an 8" cement treatment. Once the subgrade achieved the final design strength, it was prime coated and overlayed with 4" of P-401 Asphalt Pavement, placed in two lifts. Once paving operations were complete, the runway markings were applied, existing runway lights were adjusted to the appropriate heights, and the shoulders were graded to match the final asphalt elevation.

Innovative Approach

This project was the first of its kind in Missouri. The existing runway was subjected to a full-depth reclamation process, which involved pulverizing the asphalt surface to a depth of 12 inches. This was followed by trimming the material to the final subgrade elevation and applying an 8-inch cement treatment. The result was a strong and stable subgrade. By using this method, we minimized the amount of material removed from the site and reduced the amount of new asphalt needed to meet the FAA's design requirements.

Want to learn more about this project?

Contact Us

More Case Studies

University of Missouri

University of Missouri Summer Paving

  • asphalt
  • hauling
  • Service Page Icon
DJI_20230828073411_0143_D

Fixing Access to Rural Missouri (FARM) Bridge Program

  • construction
Altona Solar Missouri

Altona – Solar

  • construction